First Phase of C-5 South Link Project to Open by March 2019

The first phase of C5 South Link Expressway will be operational by March 2019--three months ahead of its planned delivery date on June next year.

@dpwh.gov.ph

"CIC is nearly halfway in terms of construction accomplishment. They are currently working on the 2.2-kilometer Segment 3A-1 from SLEX/C5 Road to Merville, crossing on top of PNR station by the Skyway at grade between Nichols Toll Plaza and Bicutan. We expect to complete this segment by March 2019," according to Public Works and Highways Secretary Mark A. Villar.

When completely finished, the C5 South Link Project will connect the Manila–Cavite Expressway or Coastal Road in Parañaque City to Circumferential Road 5 (C-5) in Taguig City.

Cavitex Infrastructure Corp. (CIC) of the Metro Pacific Tollways Corp. (MPTC) said that around 75 percent of the right-of-way has already been resolved for the first phase. However, some are still being processed--particularly seven structures of Manila International Airport Authority (MIAA) and five structures of the Philippine National Police (PNP).

"Na-resolve 'yung right of way at MIAA. So we're able to access that. Syempre 'yung mga ganitong projects kasi you just have to push the contractor… So contractually they have to finish in June, pero sabi namin agahan natin, (We already resolved the right of way at MIAA. So we’re able to access that. Of course, in project like these, you just have to push the contractor…So contractually, they have to finish in June, but we told them to finish earlier)" CIC President Luigi L. Bautista told reporters.

C-5 South Link Project

The government hopes that the 10-billion, 7.7 km toll road will cut the travel time of Paranaque, Cavite, and Las Piñas motorists heading to Taguig from an hour to 20-30 minutes.

The first phase, which covers the first 2.2 kilometers from the C5 road to Merville, is to be completed on the first quarter of 2019. Meanwhile, the second phase from Merville to Sucat will possibly be opened by 2019 as well. The third phase, which stretches from Sucat to R1 Expressway, is expected to be opened by 2020.

"We'll open another phase by 2019, then we'll open another phase by 2020…. Pero at least, as early as next year, first quarter, mapapakinabangan na itong C5 link, (But at least, as early as first quarter of next year, we will get to utilize the C5 link)" Villar said.

Read All

Featured Articles

Recommended Articles For You

Read All

Featured Cars

  • Upcoming

Car Articles From Zigwheels

  • News
  • Article Feature
  • Advisory Stories
  • Road Test
  • Diaz's manager says conditions of ‘free fuel for life’ reward raised only after 2 years 
    Diaz's manager says conditions of ‘free fuel for life’ reward raised only after 2 years 
    Paulo Papa . Mar 13, 2026
  • MG Iloilo gets back-to-back DOYA honor
    MG Iloilo gets back-to-back DOYA honor
    Ruben Manahan IV . Mar 13, 2026
  • Grab, Move It partners to get ‘immediate support’ for fuel price surge
    Grab, Move It partners to get ‘immediate support’ for fuel price surge
    Paulo Papa . Mar 13, 2026
  • Lexus PH to display lineup at 2026 Toyota Gazoo Racing Philippine Cup opener
    Lexus PH to display lineup at 2026 Toyota Gazoo Racing Philippine Cup opener
    Ruben Manahan IV . Mar 13, 2026
  • Ford PH hailed as top corporate taxpayer in Muntinlupa City
    Ford PH hailed as top corporate taxpayer in Muntinlupa City
    Cesar Miguel . Mar 13, 2026
  • Luxury MPV showdown: Denza D9 vs. Lexus LM
    Luxury MPV showdown: Denza D9 vs. Lexus LM
    Cesar Miguel . Mar 13, 2026
  • Women in the Philippine auto industry
    Women in the Philippine auto industry
    Paulo Papa . Mar 13, 2026
  • A closer look at Mitsubishi Versa Van’s pros, cons
    A closer look at Mitsubishi Versa Van’s pros, cons
    Cesar Miguel . Mar 12, 2026
  • Check out the updated Honda CR-V’s variants
    Check out the updated Honda CR-V’s variants
    Cesar Miguel . Mar 11, 2026
  • GWM Haval H9: Is it priced right?
    GWM Haval H9: Is it priced right?
    Paulo Papa . Mar 09, 2026
  • How to prepare your car for summer
    How to prepare your car for summer
    Cesar Miguel . Mar 11, 2026
  • Avoid road trip horror stories this 'Undas' with these tips
    Avoid road trip horror stories this 'Undas' with these tips
    Ruben Manahan IV . Oct 20, 2025
  • Here are ways to avoid road rage
    Here are ways to avoid road rage
    Paulo Papa . Sep 23, 2025
  • How well do you understand traffic signs?
    How well do you understand traffic signs?
    Cesar Miguel . Sep 09, 2025
  • How car collectors can take advantage of Liqui Moly products
    How car collectors can take advantage of Liqui Moly products
    Ruben Manahan IV . Sep 08, 2025
  • BYD DM-i lineup conquers Southern Luzon
    BYD DM-i lineup conquers Southern Luzon
    Cesar Miguel . Mar 10, 2026
  • Hyundai Creta Premium: balancing engaging drive,comfort
    Hyundai Creta Premium: balancing engaging drive,comfort
    Cesar Miguel . Feb 13, 2026
  • First drive: 4th-gen Changan CS55 Plus
    First drive: 4th-gen Changan CS55 Plus
    Paulo Papa . Feb 09, 2026
  • Changan CS15: small upgrades makes the difference
    Changan CS15: small upgrades makes the difference
    Cesar Miguel . Feb 06, 2026
  • First drive: Changan Eado Plus
    First drive: Changan Eado Plus
    Paulo Papa . Feb 03, 2026