First Phase of C-5 South Link Project to Open by March 2019

The first phase of C5 South Link Expressway will be operational by March 2019--three months ahead of its planned delivery date on June next year.

@dpwh.gov.ph

"CIC is nearly halfway in terms of construction accomplishment. They are currently working on the 2.2-kilometer Segment 3A-1 from SLEX/C5 Road to Merville, crossing on top of PNR station by the Skyway at grade between Nichols Toll Plaza and Bicutan. We expect to complete this segment by March 2019," according to Public Works and Highways Secretary Mark A. Villar.

When completely finished, the C5 South Link Project will connect the Manila–Cavite Expressway or Coastal Road in Parañaque City to Circumferential Road 5 (C-5) in Taguig City.

Cavitex Infrastructure Corp. (CIC) of the Metro Pacific Tollways Corp. (MPTC) said that around 75 percent of the right-of-way has already been resolved for the first phase. However, some are still being processed--particularly seven structures of Manila International Airport Authority (MIAA) and five structures of the Philippine National Police (PNP).

"Na-resolve 'yung right of way at MIAA. So we're able to access that. Syempre 'yung mga ganitong projects kasi you just have to push the contractor… So contractually they have to finish in June, pero sabi namin agahan natin, (We already resolved the right of way at MIAA. So we’re able to access that. Of course, in project like these, you just have to push the contractor…So contractually, they have to finish in June, but we told them to finish earlier)" CIC President Luigi L. Bautista told reporters.

C-5 South Link Project

The government hopes that the 10-billion, 7.7 km toll road will cut the travel time of Paranaque, Cavite, and Las Piñas motorists heading to Taguig from an hour to 20-30 minutes.

The first phase, which covers the first 2.2 kilometers from the C5 road to Merville, is to be completed on the first quarter of 2019. Meanwhile, the second phase from Merville to Sucat will possibly be opened by 2019 as well. The third phase, which stretches from Sucat to R1 Expressway, is expected to be opened by 2020.

"We'll open another phase by 2019, then we'll open another phase by 2020…. Pero at least, as early as next year, first quarter, mapapakinabangan na itong C5 link, (But at least, as early as first quarter of next year, we will get to utilize the C5 link)" Villar said.

Read All

Featured Articles

Recommended Articles For You

Read All

Featured Cars

  • Upcoming

Car Articles From Zigwheels

  • News
  • Article Feature
  • Advisory Stories
  • Road Test
  • Suzuki Fronx gets 5-star ASEAN NCAP rating
    Suzuki Fronx gets 5-star ASEAN NCAP rating
    Ruben Manahan IV . Today
  • Toyota set to unveil “bZ Time Attack” AWD Concept at SEMA 2025
    Toyota set to unveil “bZ Time Attack” AWD Concept at SEMA 2025
    Cesar Miguel . Today
  • MMPC commences coastal cleanup activity along Laguna Lake’s shorelines
    MMPC commences coastal cleanup activity along Laguna Lake’s shorelines
    Cesar Miguel . Today
  • Zigwheels PH monthly wrap: Oct. 2025
    Zigwheels PH monthly wrap: Oct. 2025
    Paulo Papa . Today
  • Michelin opens Tyreplus shop in Makati
    Michelin opens Tyreplus shop in Makati
    Ruben Manahan IV . Today
  • Cars that were recently brought back to life
    Cars that were recently brought back to life
    Paulo Papa . Oct 31, 2025
  • Check out Suzuki Fronx’s perks, drawbacks
    Check out Suzuki Fronx’s perks, drawbacks
    Cesar Miguel . Oct 29, 2025
  • Check out the BYD eMAX 9 DM-i’s 2 trims
    Check out the BYD eMAX 9 DM-i’s 2 trims
    Cesar Miguel . Oct 27, 2025
  • Top 4 reasons to buy the JAC JS6
    Top 4 reasons to buy the JAC JS6
    Cesar Miguel . Oct 21, 2025
  • Li Auto L7: 4 reasons to buy
    Li Auto L7: 4 reasons to buy
    Cesar Miguel . Oct 17, 2025
  • Avoid road trip horror stories this 'Undas' with these tips
    Avoid road trip horror stories this 'Undas' with these tips
    Ruben Manahan IV . Oct 20, 2025
  • Here are ways to avoid road rage
    Here are ways to avoid road rage
    Paulo Papa . Sep 23, 2025
  • How well do you understand traffic signs?
    How well do you understand traffic signs?
    Cesar Miguel . Sep 09, 2025
  • How car collectors can take advantage of Liqui Moly products
    How car collectors can take advantage of Liqui Moly products
    Ruben Manahan IV . Sep 08, 2025
  • Do you still need to wash your car after it rains?
    Do you still need to wash your car after it rains?
    Cesar Miguel . Jun 12, 2025
  • First drive: Mercedes-Benz GLE 400e
    First drive: Mercedes-Benz GLE 400e
    Paulo Papa . Oct 29, 2025
  • Land Rover Defender Octa: down and dirty
    Land Rover Defender Octa: down and dirty
    Paulo Papa . Oct 28, 2025
  • Mitsubishi XForce: X marks the spot
    Mitsubishi XForce: X marks the spot
    Paulo Papa . Oct 27, 2025
  • First drive: Ford Territory Hybrid
    First drive: Ford Territory Hybrid
    Cesar Miguel . Oct 16, 2025
  • Honda HR-V S: well-endowed entry level option
    Honda HR-V S: well-endowed entry level option
    Cesar Miguel . Oct 06, 2025