SMC resumes work on Skyway extension, devises new traffic scheme

sanmiguel.com.ph

San Miguel Infrastructure, San Miguel Corporation’s construction arm and the concession holder for the Metro Manila Skyway, announced the resumption of work on the Skyway extension covering some of the sections in Sucat and Alabang, following the Metro’s transition from modified enhanced community quarantine (MECQ) to general community quarantine (GCQ) this June 1.

The construction of the project was put to a grinding halt for two months with the implementation of the   community quarantine (ECQ) mid-March.

sanmiguel.com.ph

Ramon Ang, SMC president and chief operating officer, said the company seeks to get back on track on the construction of the projects following the work suspension lasting more than two months.

Along with the resumption of work, Ang announced the closure of the Skyway Alabang Toll Plaza Southbound entry from May 31 to June 15.

SMC said the road closure will allow for the commencement of bored piling works at the southbound section.

SMC also closed about 700 meters of Lane 3 of the Skyway at-grade section northbound from the old Alabang Entry Plaza. This is for the installation of scaffoldings necessary to build the columns for Pier 34 to 49, the conglomerate announced.

Due to the scheduled month-long road closure, Skyway management, with the help of the Muntinlupa Traffic Management Bureau, will be implementing a new traffic scheme for the riding public to follow.

Skyway management is advising private cars to take Filinvest Entry and/or National Road to Susana Heights entry, while trucks and buses are instructed to take National Road to Susana Heights entry.

sanmiguel.com.ph

The Skyway extension project, which was originally slated for a December 2020 completion date, will have its projection numbers readjusted to accommodate the COVID-19 pandemic and its aftermath.

Once completed, the extension project will see Skyway provide motorists with access from Susana Heights in SLEX to Sucat and back, along with a direct to the elevated section of the Skyway. The project will also increase the number of lanes on both directions to five northbound and four southbound.

With these provisions, the project is expected to significantly ease traffic to and from the south.

Photos from San Miguel Corporation

Also read:

JICA Solidifies Commitment to Help PH with Traffic Woes

Baguio to Employ 4Es to Fix Worsening Traffic

Read All

Featured Articles

Recommended Articles For You

Read All

Featured Cars

  • Upcoming

Car Articles From Zigwheels

  • News
  • Article Feature
  • Advisory Stories
  • Road Test
  • Nissan PH appoints Kanazawa as president
    Nissan PH appoints Kanazawa as president
    Ruben Manahan IV . Today
  • Toyota introduces motorsport-bred improvements for GR Yaris
    Toyota introduces motorsport-bred improvements for GR Yaris
    Cesar Miguel . Today
  • HOR to fast-track mandatory biofuel blending requirements
    HOR to fast-track mandatory biofuel blending requirements
    Ruben Manahan IV . Mar 16, 2026
  • Honda cancels upcoming 0 SUV, 0 Saloon, Acura RSX EV models
    Honda cancels upcoming 0 SUV, 0 Saloon, Acura RSX EV models
    Cesar Miguel . Mar 16, 2026
  • ASEAN NCAP revokes new Proton X90’s 5-star rating
    ASEAN NCAP revokes new Proton X90’s 5-star rating
    Ruben Manahan IV . Mar 16, 2026
  • Luxury MPV showdown: Denza D9 vs. Lexus LM
    Luxury MPV showdown: Denza D9 vs. Lexus LM
    Cesar Miguel . Mar 13, 2026
  • Women in the Philippine auto industry
    Women in the Philippine auto industry
    Paulo Papa . Mar 13, 2026
  • A closer look at Mitsubishi Versa Van’s pros, cons
    A closer look at Mitsubishi Versa Van’s pros, cons
    Cesar Miguel . Mar 12, 2026
  • Check out the updated Honda CR-V’s variants
    Check out the updated Honda CR-V’s variants
    Cesar Miguel . Mar 11, 2026
  • GWM Haval H9: Is it priced right?
    GWM Haval H9: Is it priced right?
    Paulo Papa . Mar 09, 2026
  • Tips on how to prevent vehicle fires
    Tips on how to prevent vehicle fires
    Cesar Miguel . Today
  • How to prepare your car for summer
    How to prepare your car for summer
    Cesar Miguel . Mar 11, 2026
  • Avoid road trip horror stories this 'Undas' with these tips
    Avoid road trip horror stories this 'Undas' with these tips
    Ruben Manahan IV . Oct 20, 2025
  • Here are ways to avoid road rage
    Here are ways to avoid road rage
    Paulo Papa . Sep 23, 2025
  • How well do you understand traffic signs?
    How well do you understand traffic signs?
    Cesar Miguel . Sep 09, 2025
  • BYD DM-i lineup conquers Southern Luzon
    BYD DM-i lineup conquers Southern Luzon
    Cesar Miguel . Mar 10, 2026
  • Hyundai Creta Premium: balancing engaging drive,comfort
    Hyundai Creta Premium: balancing engaging drive,comfort
    Cesar Miguel . Feb 13, 2026
  • First drive: 4th-gen Changan CS55 Plus
    First drive: 4th-gen Changan CS55 Plus
    Paulo Papa . Feb 09, 2026
  • Changan CS15: small upgrades makes the difference
    Changan CS15: small upgrades makes the difference
    Cesar Miguel . Feb 06, 2026
  • First drive: Changan Eado Plus
    First drive: Changan Eado Plus
    Paulo Papa . Feb 03, 2026