The portion of the Skyway Stage 3 that has been gutted by fire early this year has already been replaced, the leadership of the Department Public Works and Highways (DPWH) announced.

According to Public Works and Highways Secretary Mark Villar, the replacement of the section that collapsed due to fire back in February 2020 was replaced as concessionaire Citra Central Expressway Corporation (CCEC) hastened civil works on the project to make up for the delay. 

“As of latest report, lower and upper coping beams for pier 3, 4, 5 were reconstructed, and deck slab for spans 5 and 6 were completed as well. These were the burned sections from the fire incident,” Villar was quoted as saying. 

The public works chief also said that the Skyway Stage 3 project is at 88.72 percent. However the said accomplishment does not cover the Section 2A or the Tomas Claudio-PUP Sta. Mesa segment.

skyway repair

“We are intensifying our road right-of-way acquisition so we may soon begin construction at Section 2A. So far, we have acquired 231 out of the 350 lots that need to be acquired with permit to enter,” Villar noted. 

Aside from that, Villar stated that the the Section 1 of the project, who covers Buendia-Quirino-Nagtahan is now at 90.67 percent; Section 2A (Nagtahan-Tomas Claudio) is at 77.23 percent; Section 2B (Tomas Claudio-Ramon Magsaysay Avenue) is 94.39 percent; Section 3 (Ramon Magsaysay-Quezon Avenue) is at 96.86 percent; Section 4 (Quezon Avenue-Balintawak, Quezon City) has reached 75.67 percent; and Section 5 (Balintawak to North Luzon Expressway Footbridge) is 83.56 percent finished. 

dpwh logo

When the whole project is accomplished, the 18.83-kilometer Skyway Stage 3 is targeted cut travel time between Buendia to Balintawak from the current two hours to only 15 to 20 minutes and can cater to an average of 55,000 vehicles every day. 

The said road project will also be the direct toll road link between NLEX and South Luzon Expressway (SLEX). 

Photo/s from Department of Public Works and Highways

Also read:

BGC to Ortigas Center in 11 minutes? Possible in 2021, Villar Claims

 Final section of TPLEX opens to the public

 NLEX Tambobong Interchange now open

Read All

Featured Articles

Recommended Articles For You

Read All

Featured Cars

  • Upcoming

Car Articles From Zigwheels

  • News
  • Article Feature
  • Advisory Stories
  • Road Test
  • Toyota Motor PH looking for top 3 candidates for GR eSports GT Championship Asia Finals
    Toyota Motor PH looking for top 3 candidates for GR eSports GT Championship Asia Finals
    Cesar Miguel . Today
  • Caltex to open service facility in CALAX
    Caltex to open service facility in CALAX
    Ruben Manahan IV . Today
  • GWM PH gets more local industry vets to join team
    GWM PH gets more local industry vets to join team
    Ruben Manahan IV . Today
  • EV industry-related concerns eyed to be addressed at 13th PEVS
    EV industry-related concerns eyed to be addressed at 13th PEVS
    Cesar Miguel . Today
  • Nissan ends R35 GT-R production
    Nissan ends R35 GT-R production
    Cesar Miguel . Aug 27, 2025
  • Here are the Lynk & Co 08 EM-P’s strengths, weaknesses
    Here are the Lynk & Co 08 EM-P’s strengths, weaknesses
    Cesar Miguel . Today
  • Check out the Toyota Land Cruiser’s key competitors
    Check out the Toyota Land Cruiser’s key competitors
    Cesar Miguel . Aug 26, 2025
  • Colorful Filipino nicknames for iconic car models
    Colorful Filipino nicknames for iconic car models
    Cesar Miguel . Aug 22, 2025
  • Here are the JMC Vigus' 2 options in PH
    Here are the JMC Vigus' 2 options in PH
    Paulo Papa . Aug 20, 2025
  • Check out the Omoda C5's 3 trims
    Check out the Omoda C5's 3 trims
    Paulo Papa . Aug 19, 2025
  • Do you still need to wash your car after it rains?
    Do you still need to wash your car after it rains?
    Cesar Miguel . Jun 12, 2025
  • What should you visit first at MIAS 2025?
    What should you visit first at MIAS 2025?
    Cesar Miguel . Apr 11, 2025
  • Do you really need 4x4 for overlanding?
    Do you really need 4x4 for overlanding?
    Cesar Miguel . Mar 26, 2025
  • Number coding 2025: what you need to know
    Number coding 2025: what you need to know
    Paulo Papa . Mar 09, 2025
  • EVs still require lubrication, JAMA execs say
    EVs still require lubrication, JAMA execs say
    Paulo Papa . Mar 09, 2025
  • First drive: Here’s why the Li Mega is the ideal pick for those who wants to be chauffeured
    First drive: Here’s why the Li Mega is the ideal pick for those who wants to be chauffeured
    Paulo Papa . Aug 27, 2025
  • GWM Cannon: range day
    GWM Cannon: range day
    Paulo Papa . Jul 29, 2025
  • First drive: BYD Sealion 5 DM-i
    First drive: BYD Sealion 5 DM-i
    Cesar Miguel . Jul 21, 2025
  • Honda BR-V S CVT: all about that ‘base’
    Honda BR-V S CVT: all about that ‘base’
    Paulo Papa . Jul 09, 2025
  • Dongfeng Rich 7 4X4 Upper: ideal entry-level truck
    Dongfeng Rich 7 4X4 Upper: ideal entry-level truck
    Paulo Papa . Jul 07, 2025