DPWH breaches halfway point of Davao City Road Mountain Tunnel Project

DPWH breaches halfway point of Davao City Road Mountain Tunnel Project

After more than two years, the Department of Public Works and Highways (DPWH) has completed about 1.3-kilometers of tunnel civil works for the Davao City Bypass Construction Project.

KEY TAKEAWAYS

  • How long is the Davao City Bypass Construction Project?

    The project, when completed, will be 45.5 kilometers long.
  • How much travel time will be improved when the project is completed?

    Per DPWH, the Davao City Bypass Construction Project will improve travel time to just 49 minutes from the current one hour and 45 minutes via Maharlika Highway.
  • DPWH Undersecretary Emil Sadain shared to Secretary Manuel Bonoan that the equipment and manpower resources of the contractor Shimizu-Ulticon-Takenaka joint venture are working at northbound and southbound directions on both ends of the north and south portals of the twin tube double-lane road mountain tunnel project.  

    Set to be 45.5 kilometers long, the Davao City Bypass Construction Project is among the infrastructure flagship projects started under the previous administration’s “Build Build Build” program and was continued under the “Build Better More” development agenda of President Ferdinand Marcos Jr. to decongest traffic and reduce travel time.  

    The on-going contract package 1-1 costing P13.23 billion is financed by a Special Terms for Economic Partnership (STEP) loan between the Philippine government and the Japan International Cooperation Agency (JICA).

    The on-going tunnel both in southbound and northbound direction involves tunnel excavation, shotcrete works for excavation face, installation of steel ribs, wire mesh and final shotcrete, drilling and installation of rock bolts.   

    DPWH breaches halfway point of Davao City Road Mountain Tunnel Project

    Per Sadain, the tunnel’s two ends in the north and south portal are targeted to break or hole through by February 2024.  

    Aside from the twin tube 10-meter wide and eight-meter high tunnel, the contract package 1-1 involves the construction of four lanes portland concrete cement pavement road with the total length of 7.9 kilometers, three pairs of bridge with the total length of 500 linear meters, two underpasses, two overpasses, 12 box culverts, and four at grade road crossings

    Package I starts in Davao-Digos Section of the Pan-Philippine Highway at Barangay Sirawan, South of Toril, Davao City approximately 500 meters south of Lipadas Bridge. It will continue on a north-northwest direction towards Barangays Marapangi and Bato where it will shift slightly northwest direction upon crossing Lipadas River and will traverse Barangays Lubogan, Alambre, Bangakas Heights and will swerve northward into Barangays Mulig and Bago Oshiro until it reaches the University of Philippines-Mindanao Campus in Barangay Marapangi Mintal.  

    The alignment passes Tugbok Proper and will traverse the Davao-Bukidnon Road, cross the Talomo River and proceed on a northwesterly direction towards agricultural lands in Barangays Tacunan and Matina-Biao, cross Matina River, before it proceeds to the tunnel section in Barangay Magtuod. 

    After the tunnel section, it will continue in the same direction towards Barangay Waan, cross Davao River and continue towards Barangay Tigatto. 

    DPWH breaches halfway point of Davao City Road Mountain Tunnel Project

    It will then proceed to Barangay Cabantian, where the alignment will shift into a northerly direction as it crosses Lasang River and passes towards Barangays Communal, Indangan, Mudiang, and Tibungco.  

    The alignment will then shift in a northward to northwestern direction as it passes through Barangay Mahayag, and makes another shift towards a northeasterly track as it approaches Barangays San Isidro and Lasang. It will continue in the same direction until it crosses with the Davao-Agusan National Highway in Barangay J.P. Laurel, Panabo City where the alignment will end. 

    According to the DPWH, the Davao City Bypass Construction Project will improve the transport logistics and mitigate congestions in Davao City with travel time of just 49 minutes from the current an hour and 45 minutes via Maharlika Highway.

    Photos from Department of Public Works and Highways

    Also read:

    Central Luzon roads improved

    Lawmaker pushes for bigger DPWH budget for 2023

    Dasmariñas-GMA-Carmona Diversion Road to be completed in 2026

    Read All

    Featured Articles

    Recommended Articles For You

    Read All

    Featured Cars

    • Upcoming

    Car Articles From Zigwheels

    • News
    • Article Feature
    • Advisory Stories
    • Road Test
    • Isuzu PH holds 20th Service Skills Olympics
      Isuzu PH holds 20th Service Skills Olympics
      Ruben Manahan IV . May 02, 2025
    • Honda Cars PH digitalizes aftermarket services
      Honda Cars PH digitalizes aftermarket services
      Cesar Miguel . May 02, 2025
    • BYD, ACMobility further push electrified mobility in Cebu
      BYD, ACMobility further push electrified mobility in Cebu
      Ruben Manahan IV . May 02, 2025
    • Mercedes-Benz to add 2 PHEV models in PH lineup soon
      Mercedes-Benz to add 2 PHEV models in PH lineup soon
      Ruben Manahan IV . May 02, 2025
    • Isuzu starts producing electrified D-Max
      Isuzu starts producing electrified D-Max
      Ruben Manahan IV . May 02, 2025
    • 5 reasons the Lexus LBX should be your main luxury city crossover pick
      5 reasons the Lexus LBX should be your main luxury city crossover pick
      Paulo Papa . May 02, 2025
    • Work wheels: vehicles that help industries move
      Work wheels: vehicles that help industries move
      Paulo Papa . Apr 30, 2025
    • Let’s check out the Nissan Patrol's classy interior
      Let’s check out the Nissan Patrol's classy interior
      Cesar Miguel . Apr 30, 2025
    • Here are the BYD eMAX 7's 4 hues
      Here are the BYD eMAX 7's 4 hues
      Paulo Papa . Apr 28, 2025
    • Isuzu mu-X's 5 elegant hues in PH
      Isuzu mu-X's 5 elegant hues in PH
      Cesar Miguel . Apr 28, 2025
    • What should you visit first at MIAS 2025?
      What should you visit first at MIAS 2025?
      Cesar Miguel . Apr 11, 2025
    • Do you really need 4x4 for overlanding?
      Do you really need 4x4 for overlanding?
      Cesar Miguel . Mar 26, 2025
    • Number coding 2025: what you need to know
      Number coding 2025: what you need to know
      Paulo Papa . Mar 09, 2025
    • EVs still require lubrication, JAMA execs say
      EVs still require lubrication, JAMA execs say
      Paulo Papa . Mar 09, 2025
    • Ensure your vehicle is Summer road trip-ready by following these tips
      Ensure your vehicle is Summer road trip-ready by following these tips
      Paulo Papa . Mar 06, 2025
    • First drive: Suzuki Dzire Hybrid
      First drive: Suzuki Dzire Hybrid
      Cesar Miguel . May 02, 2025
    • Kia Sorento Turbo Hybrid's 4 unique features vs. most midsize SUVs
      Kia Sorento Turbo Hybrid's 4 unique features vs. most midsize SUVs
      Ruben Manahan IV . Apr 30, 2025
    • First drive: Changan Lumin
      First drive: Changan Lumin
      Cesar Miguel . Apr 22, 2025
    • JAC JS4: from daily drives to ‘vacay’ vibes
      JAC JS4: from daily drives to ‘vacay’ vibes
      Paulo Papa . Apr 22, 2025
    • First drive: Jetour X70 Lightning i-DM
      First drive: Jetour X70 Lightning i-DM
      Paulo Papa . Apr 03, 2025