Estrella-Pantaleon Bridge to be opened H1 2021

Estrella Pantaleon Bridge

The leadership of the Department of Public Works and Highways (DPWH) claimed that they will be opening the upgraded Estrella-Pantaleon Bridge come first half of 2021.

After a technical inspection Wednesday (January 6, 2021), Public Works and Highways Secretary Mark Villar made the announcement, saying that motorists can use the widened and modernized bridge (that connects Estrella Street in Makati City and Barangka Drive in Mandaluyong City) by second half of the year. 

Villar also claimed that the construction work is now more than 72 percent complete—8 percent ahead of schedule. 

Etsrella-Pantaleon Bridge

DPWH claimed that they have already completed all bridge substructure abutment works on both sides; piers on Makati approach as well as main bridge; as well as the V-shaped piers for the main bridge.

Aside from that, they are also done with the concrete pouring works for four segments of prestressed concrete girder on the Mandaluyong side and concrete pouring works for the first lift of box girder for the approach bridge on Makati.

The department claimed that the accelerated schedule was due to Villar’s instruction to the DPWH- Unified Project Management Office (UPMO) to proceed more quickly so that the bridge can be opened for public use earlier.

Villar noted that said that DPWH UPMO under the direction of Undersecretary Emil Sadain is doing all necessary measures to ensure quality standards and safety and to keep up with the pandemic-related challenges and backlog.

Estrella-Pantaleon Bridge

Meanwhile, Sadain said that their Roads Management Cluster 1 is currently working on the remaining civil works covering formworks and rebar installation in two segments of prestressed concrete girder in Mandaluyong side and two more segments in Makati side as well as for the second lift of box girder for the approach bridge in Makati side in order to complete the bridge.

Once opened, the public can expect traffic relief by providing additional fix link and alternative route crossing the Pasig River using a new two-way four-lane bridge with a total length of 506.46 meters and width of 21.65 meters, having 3-meter sidewalks on both sides.

Prior to this, the closure for the bridgework was deferred many times since 2018 and was finally closed January 2019.

The said bridge, which is part of the efforts to decongest EDSA, is funded by a grant from China.

Photos from Department of Public Works and Highways

Also read:

Completion of Estrella-Pantaleon, Binondo-Intramuros Bridges still on schedule

Estrella-Pantaleon Bridge to be Closed Starting January 19

Expect Longer Commute Time Once the Estrella-Pantaleon Rehabilitation Starts This Week

Read All

Featured Articles

Recommended Articles For You

Read All

Featured Cars

  • Upcoming

Car Articles From Zigwheels

  • News
  • Article Feature
  • Advisory Stories
  • Road Test
  • Marcos Jr. vetoes budgets for auto industry-related programs
    Marcos Jr. vetoes budgets for auto industry-related programs
    Ruben Manahan IV . Jan 06, 2026
  • Toyota, Lexus PH issue recall orders over faulty parking view assist ECU
    Toyota, Lexus PH issue recall orders over faulty parking view assist ECU
    Ruben Manahan IV . Jan 06, 2026
  • Nissan to create next-gen ProPILOT
    Nissan to create next-gen ProPILOT
    Ruben Manahan IV . Jan 06, 2026
  • Ford favors EREVs, hybrids, smaller all-electric models over big EVs
    Ford favors EREVs, hybrids, smaller all-electric models over big EVs
    Cesar Miguel . Jan 06, 2026
  • Geely Motor PH to launch EX-5 EM-i this year?
    Geely Motor PH to launch EX-5 EM-i this year?
    Cesar Miguel . Jan 06, 2026
  • New year, new ride: Toyota Land Cruiser FJ
    New year, new ride: Toyota Land Cruiser FJ
    Paulo Papa . Jan 05, 2026
  • New year, new ride: GWM Haval H9
    New year, new ride: GWM Haval H9
    Paulo Papa . Jan 05, 2026
  • New year, new ride: all-new Honda Prelude
    New year, new ride: all-new Honda Prelude
    Paulo Papa . Jan 02, 2026
  • New year, new ride: next-gen Toyota Hilux
    New year, new ride: next-gen Toyota Hilux
    Cesar Miguel . Jan 02, 2026
  • Zigwheels PH most viewed for 2025: Toyota Fortuner
    Zigwheels PH most viewed for 2025: Toyota Fortuner
    Cesar Miguel . Dec 29, 2025
  • Avoid road trip horror stories this 'Undas' with these tips
    Avoid road trip horror stories this 'Undas' with these tips
    Ruben Manahan IV . Oct 20, 2025
  • Here are ways to avoid road rage
    Here are ways to avoid road rage
    Paulo Papa . Sep 23, 2025
  • How well do you understand traffic signs?
    How well do you understand traffic signs?
    Cesar Miguel . Sep 09, 2025
  • How car collectors can take advantage of Liqui Moly products
    How car collectors can take advantage of Liqui Moly products
    Ruben Manahan IV . Sep 08, 2025
  • Do you still need to wash your car after it rains?
    Do you still need to wash your car after it rains?
    Cesar Miguel . Jun 12, 2025
  • Ford Ranger Raptor V6: off-road conqueror is a decent daily driver
    Ford Ranger Raptor V6: off-road conqueror is a decent daily driver
    Cesar Miguel . Today
  • ELECTRIA: Changan Hunter 4x4 Knight is crushing stigma around pickup trucks
    ELECTRIA: Changan Hunter 4x4 Knight is crushing stigma around pickup trucks
    Ruben Manahan IV . Jan 02, 2026
  • First drive: Radar RD6 Econ
    First drive: Radar RD6 Econ
    Cesar Miguel . Dec 02, 2025
  • Changan Nevo Q05: efficiently speedy
    Changan Nevo Q05: efficiently speedy
    Cesar Miguel . Nov 25, 2025
  • ELECTRIA: VinFast VF 3 - When simplicity just works
    ELECTRIA: VinFast VF 3 - When simplicity just works
    Cesar Miguel . Nov 24, 2025