Cabanatuan-bound CLLEX Segment to be partially open by yearend

Cclex Cabanatuan

The major segment of Central Luzon Link Expressway (CLLEX) Phase 1 leading Cabanatuan City is set to be completed by end of this year. 

Department of Public Works and Highways (DPWH) Undersecretary for Unified Project Management Office (UPMO) Operations & Technical Services Emil Sadain said that construction of the 4-lane 30-kilometer (km) expressway from the connecting road in SCTEX (Subic-Clark-Tarlac Expressway) and TPLEX (Tarlac-Pangasinan-La Union Expressway) in Balincanaway, Tarlac City and ends at Daang Maharlika in Caalibangbangan, Cabanatuan City is 82 percent completed and being fast-tracked with about 25-km stretch targeted to open by December 2020.

CLLEx Cabanatuan Sadain

Sadain said despite the work suspension order imposed from March 20 due to announcement of lockdown of the entire Luzon under enhanced community quarantine amid COVID-19 pandemic, the first three contract packages (CP) and substantial portion of CP-4 will be completed this year as construction activities have immediately resumed on May 5. 

The 4.1-km CP-1 Tarlac Section is already completed including the 300 meter temporary off and on-ramp constructed at the beginning of Rio Chico River Bridge Section or CP-2.

The 6.4-km CP-2 which involves the construction of 1.5 km Rio Chico River viaduct, 42 meter Sta Lucia River Bridge, 38 meter La Paz-Victoria underpass bridge is 94.78 percent finished.

Further, the 9.2 km CP-3 covering Aliaga section which includes the construction of 42 meter Guimba-Aliaga underpass bridge and Aliaga interchange is 67.83 percent completed.

Construction of 10.3-km CP-4 or Cabanatuan Section which also covers Cabanatuan and San Juan interchanges is 68.65 percent completed.

Upon full completion of the entire alignment, CLLEX Phase 1 will cut travel time between Tarlac City and Cabanatuan City from 70 minutes to just 20 minutes and around 11,200 motorists and commuters would benefit by CLLEX daily and ease traffic at Daang Maharlika Highway by about 48 percent. 

CLLEX Cabanatuan

Moreover, an additional 4.8-km component of the expressway project from the junction of Carmen-Cabanatuan Road is the Zaragoza Interchange section which comprises of 2.8-km access free road and 2-km interchange ramp that will cross over the embankment of CLLEX main expressway by an overpass.

Back in May last year, DPWH Secretary Mark Villar announced that the construction of the Central Luzon Link Expressway (CLLEX) Phase 1, Contract Package 1, that the Contract Package 1 with a budget amounting to PHP1.603 billion is now 97-percent completed.

Photos from Department of Public Works and Highways 

 Also read:

Drilon says Build, Build, Build a 'dismal failure', Panelo shrugs off claims

Bypass Road, Disaster Mitigation Projects in Central Luzon being fast-tracked

Read All

Featured Articles

Recommended Articles For You

Read All

Featured Cars

  • Upcoming

Car Articles From Zigwheels

  • News
  • Article Feature
  • Advisory Stories
  • Road Test
  • Updated VinFast VF 8 launched in Vietnam, will it come to PH soon?
    Updated VinFast VF 8 launched in Vietnam, will it come to PH soon?
    Paulo Papa . May 24, 2026
  • Ford PH could be launching a V6-powered Everest soon
    Ford PH could be launching a V6-powered Everest soon
    Cesar Miguel . May 22, 2026
  • MG cars destroyed in 2025 fire incident to be ‘responsibly’ disposed of
    MG cars destroyed in 2025 fire incident to be ‘responsibly’ disposed of
    Paulo Papa . May 22, 2026
  • In 8 pictures: GAC International PH launches Aion UT
    In 8 pictures: GAC International PH launches Aion UT
    Cesar Miguel . May 21, 2026
  • Deepal puts up flagship dealership in PH
    Deepal puts up flagship dealership in PH
    Cesar Miguel . May 21, 2026
  • Check out the Toyota bZ4X's 4 electrifying tones
    Check out the Toyota bZ4X's 4 electrifying tones
    Paulo Papa . May 20, 2026
  • Check out the MG G50 PHEV’s strengths, weaknesses
    Check out the MG G50 PHEV’s strengths, weaknesses
    Cesar Miguel . May 19, 2026
  • Check out the VinFast VF MPV 7’s closest competitor
    Check out the VinFast VF MPV 7’s closest competitor
    Cesar Miguel . May 18, 2026
  • How did ‘Morizo’ start in motorsports?
    How did ‘Morizo’ start in motorsports?
    Ruben Manahan IV . May 18, 2026
  • Check out the Jaecoo J5 SHS-S’ similarly-sized rivals
    Check out the Jaecoo J5 SHS-S’ similarly-sized rivals
    Cesar Miguel . May 14, 2026
  • Tips on how to prevent vehicle fires
    Tips on how to prevent vehicle fires
    Cesar Miguel . Mar 17, 2026
  • How to prepare your car for summer
    How to prepare your car for summer
    Cesar Miguel . Mar 11, 2026
  • Avoid road trip horror stories this 'Undas' with these tips
    Avoid road trip horror stories this 'Undas' with these tips
    Ruben Manahan IV . Oct 20, 2025
  • Here are ways to avoid road rage
    Here are ways to avoid road rage
    Paulo Papa . Sep 23, 2025
  • How well do you understand traffic signs?
    How well do you understand traffic signs?
    Cesar Miguel . Sep 09, 2025
  • ELECTRIA: VinFast VF 6 is a well-equipped urban warrior
    ELECTRIA: VinFast VF 6 is a well-equipped urban warrior
    Cesar Miguel . Apr 20, 2026
  • BYD DM-i lineup conquers Southern Luzon
    BYD DM-i lineup conquers Southern Luzon
    Cesar Miguel . Mar 10, 2026
  • Hyundai Creta Premium: balancing engaging drive,comfort
    Hyundai Creta Premium: balancing engaging drive,comfort
    Cesar Miguel . Feb 13, 2026
  • First drive: 4th-gen Changan CS55 Plus
    First drive: 4th-gen Changan CS55 Plus
    Paulo Papa . Feb 09, 2026
  • Changan CS15: small upgrades makes the difference
    Changan CS15: small upgrades makes the difference
    Cesar Miguel . Feb 06, 2026